During my years managing bunker operations in Fujairah, I sometimes cancelled a barge's place in the port berthing queue even though her position on the list had not changed. We had expected her to load and clear the berth in time to meet a customer's vessel. What had changed was our understanding of when the berth would actually become free.
At the time, there were a limited number of berths at which bunker barges could load. Barges from several suppliers waited their turn, and the berthing list was displayed on the port's website. A delay to a seagoing vessel already alongside could affect every barge behind her. The list was useful for knowing who was ahead of us. It was less useful for judging whether a delay that had started that morning would still be affecting us when our customer arrived.
A vessel calling for bunkers often had little time to spare. From the Operations desk, we could speak to our port contacts about the berthing position and to our terminal colleagues about how cargo operations aboard the vessel alongside were progressing. Their answers helped us judge whether the original loading plan was still workable. If the berth was likely to clear soon, there was good reason to keep our place. If the delay looked likely to run into the customer's delivery window, we had another option.
We operated a converted very large crude carrier (VLCC) as a mother ship at anchorage. When conditions allowed, we could cancel the port booking and send the barge out to replenish there. We did so on a number of occasions. The arrangement also worked the other way. Fujairah's anchorage is exposed to Indian Ocean swell, and when it was unsafe to load alongside the mother ship, we could send the barge into port, subject to berth availability. Neither route could be counted on every time; between them, they gave us a choice that a place on the berthing list alone could not provide.
A further advantage concerned how much fuel we needed to load. We might have planned a full barge load to cover several deliveries, but only part of that quantity was needed by the first vessel. We could part-load at a berth as well, although the port call involved charges for services such as pilotage and tugs. Those costs made a call for a smaller quantity relatively expensive. Alongside the mother ship, we could load enough for the urgent stem, send the barge to deliver it and bring her back for the balance. The customer had no reason to wait while we loaded stock intended for somebody else.
The mother ship was permitted to load two barges simultaneously, one on either side. She took prepared product from shore and returned to port when she needed replenishing. We did not blend aboard. A small laboratory allowed us to check selected fuel parameters after loading, and we sent samples ashore to an independent laboratory when more detailed analysis was needed.
For the Operations team, the flexibility meant more work. A barge sent away partly loaded still needed a second loading slot. Her next delivery had to be planned around it, and the quantities remaining aboard both vessels had to be reconciled after each transfer. The mother ship's own return to port also had to fit the programme. It was possible to gain time for one customer and lose it on the next delivery if the office did not follow through on the change.
The charter, crew, laboratory and running costs of a VLCC were substantial. In our circumstances, there was sufficient business to justify them. I would be reluctant to draw the same conclusion for a port or a supplier with a different pattern of demand. For us, the commercial value was clearest when a customer was due and our barge was still on the berthing list. Once we had good reason to believe the berth would be too late, we could act on that information. Sometimes that meant giving up a place we had waited for, taking only the fuel we needed, and leaving the rest of the loading programme until after the customer had been served.
About the author. Capt. Qaisar Qayyum is a Master Mariner and Independent Maritime & Bunkering Adviser with more than four decades of maritime experience, including approximately 23 years at sea and two decades in senior shore based bunker operations.
He retired as General Manager, Bunkering Operations (UAE) with Vitol Bunkers, where his responsibilities included complex marine fuel operations, operational risk management, claims handling and coordination across commercial, technical and marine functions.
Drawing on experience from both shipboard and shore management perspectives, he now provides independent advisory support to shipowners, bunker suppliers, traders and maritime organisations on bunker operations, operational risk, claims prevention and marine fuel disputes, with particular emphasis on practical decision making, communication and the human factors that influence operational outcomes.
Email: [email protected]
LinkedIn: www.linkedin.com/in/qaisar-qayyum-11279018