• Grant covers 50% of costs for SME operators and 30% for larger ones, capped at S$42,000 a tanker
  • Trials to capture MFM data at least every two seconds and send it to e-BDN systems by API
  • Applications open until March 31, 2027, with projects to finish by October 31, 2027

The Maritime and Port Authority of Singapore (MPA) has opened a call for proposals offering grants of up to S$42,000 per bunker tanker for trials of automated mass flow meter data capture.

The call, which opened on November 26 and closes on March 31, 2027, is the grant round MPA trailed at SIBCON in October as the start of the second phase of its digital bunkering programme.

Funding comes from the Maritime Innovation and Technology Fund and covers up to 50% of qualifying costs where the bunker craft operator is a small or medium-sized enterprise, or up to 30% for larger operators, MPA said in the call document.

The authority said it will support up to about 10% of the licensed bunker tankers in Singapore, with one funded installation per vessel and each operator allowed to take part in up to two projects.

Proposals must come jointly from a licensed bunker craft operator and a technology provider incorporated and operating in Singapore, with the operator as the grant recipient.

The trials are to test hardware and software that captures data from a tanker's approved mass flow meter on a read-only basis at intervals of no more than two seconds, stores it unaltered, and transmits it by API to electronic bunker delivery note platforms and an MPA-designated system.

Systems must also keep working through connectivity loss and equipment failure, with buffering and retransmission, and will be assessed by the National Metrology Centre for accuracy, integrity and transmission reliability, as well as for cybersecurity.

Solutions must comply with the SS 648 mass flow metering code and the SS 709 digital bunkering documentation specification, MPA said.

Each project must run at least four months of operational trials, with completion targeted for October 31, 2027 where practicable, and applications will be approved on a rolling basis.

MPA said the findings will inform its future whitelisting requirements and wider industry adoption, but that taking part in the trials does not guarantee a solution will be whitelisted or approved.